Current Development Applications
15a-21 St Georges Crescent
Next Milestone: 27/07/2026 – end date for comments
Status: Open for comment
Lodged: 24/06/2026
Estimated Cost of Work: $ 52,408,871
Officer: Nima Salek
DA2026/0119 can be found here
55-61 St Georges Crescent
Next Milestones: Submissions 29th July 2026
On-Site meeting 9:00AM 19th Aug 2026
LEC in court hearing on 20& 21 August 2026
Status: New plan have now been submitted
Residential - New multi unit - Demolition of all existing dwellings, removal of all 18 trees, construction of a split 8 to 9 storey, 55 unit residential flat building with basement parking and consolidation of 5 lots
DA2025/0211 can be found here
113 St Georges Crescent
Next Milestone: 07/08/2026 – end date for comments
Status: Open for comment
Lodged: 24/06/2026
Estimated Cost of Work: $ 9,097,622
Officer: Kurt Savage
DA2026/0116 can be found here
76a-76b St Georges Crescent
Next Milestone: 29th July 2026, 6:00pm Online Planning Panel
Status: Under review by council
Residential - New multi unit - Demolition of existing buildings, lot amalgamation, construction of 2 residential flat buildings with 24 x 3 bedroom units including affordable housing, basement parking, landscaping and associated site works
DA2026/0048 can be found here.
72 - 76 St Georges Crescent
Status: Waiting for developer to lodge EIS
Next MIlestone: Public Exhibition
This is an SSD (State Significant Development) that is managed and adjudicated by the NSW Department of Planning, not the City of Canada Bay. The building comprises two x 10 storey buildings with 154 apartments with 15% affordable housing. Initial feedback / survey to Urbis closed on 27 April. To see the call to action for that click here.
SSD-111289990 can be found here
Shop top 63-69 Victoria Rd and 45 Day St
Status: Sears (Secretary’s Environmental Assessment Requirements)
Next Milestone: Secretary publishes SEARS for the developer to prepares a formal EIS.
This an SSD (State Significant Development) that is managed and adjudicated by the NSW Department of Planning, not the City of Canada Bay.
Located at Victoria Rd & Day St, Drummoyne – on the city side of the Kookaburra building. The existing buildings will be replaced by a 10-storey mixed-use “shop-top” development with 67 apartments (~15% affordable housing), Ground floor retail/commercial and Basement parking. It relies on the existing Victoria Rd bus services without road or transport upgrades.
SSD-112227490 can be found here
44 St Georges Crescent
Status: Under review by Council
Next Milestone: Council Decision
Residential - New multi unit - Demolition of existing buildings and structures and the erection of a new split level residential flat building with 7 levels total, 4 storeys above existing ground level, 2 to 3 levels of basement, consisting of 4 x 3 bedroom residential apartments
DA2026/0028 can be found here
297 Victoria Place
Status: Under Review by Council
Next Milestone: Council Decision
Residential - New multi unit - Demolition of existing building and construction of a five (5) storey residential development containing seven (7) residential apartments, basement car parking and associated landscape.
DA2026/0066 can be found here
3 Wolseley Street
Status: Under review by Council
Next Milestone: Council Decision
Residential - New multi unit - Demolition of existing structures and construction of a residential flat building containing 8 units over basement parking with associated landscaping
Da2026/0052 can be found here